Early April2017

Request for Quotation for Design and Build of Training Centre

Late April2017

Request for Qualifications for Deep Piling

May2017

Request for Qualifications to Bidders for QA/QC (Testing)

LateJuly2017

Request for Qualifications to Bidders for Main Plant General Contractor

Oct2018

Recruitment of Personnel

March2019

Installation of Machinery

Dec 2019

Ribbon Cutting